Initiatives we support ACCIONA.org foundation Innovation Job offers Safety and health Graduates and Internships Opportunities and inclusion Wind power Photovoltaic Thermal Solar CSP Biomass Hydroelectric Offshore wind Storage Renewable energy supply Green hydrogen Energy efficiency Electric mobility Self consumption Integrated annual report Annual accounts Results, reports and presentations Average period of payment to suppliers Rating Share price Dividends Analysts’ recommendations Investor calendar Sustainable finance General Shareholders' Meeting Board of Directors and Committees Management team Share capital Annual Corporate Governance Report Director remuneration Rules of Governance Ethics and Compliance Fixed income CNMV communications Framework agreement
13 FEB 2025

ACCIONA Energía announced today the successful completion of wind turbine installation for the Forty Mile Wind project in Bow Island, Alberta, Canada, marking a significant step forward in the project’s development.

ACCIONA Energía announced today the successful completion of wind turbine installation for the Forty Mile Wind project in Bow Island, Alberta, Canada, marking a significant step forward in the project’s development. Furthermore, the company has now connected 14 of the 49 turbines to the grid, corresponding to 80MW, meaning they are already supplying clean electricity for Alberta.

The Forty Mile Wind project consists of 49 5.7MW capacity Nordex wind turbines, each with a tower height of 108-meters. With a total installed capacity of 280MW, this project is one of Canada’s ten largest wind farms and the largest installation of its kind that ACCIONA Energia has built to date in North America. Upon full energization, the wind farm will generate enough clean energy to power more than 85,000 homes.

A team of more than 250 dedicated workers faced temperatures as low as -20˚F/-29˚C and worked around the clock in two shifts to maximize crane lifting windows and complete erection safely. Specialized safety protocols including the implementation of a winter work plan were critical in achieving this milestone.

Electrical commissioning is ongoing, and the wind farm is scheduled to be fully operational in spring 2025.